If you are the operator of a large combustion plant, gas turbine or internal combustion engine plant, you must have the pollutant emissions checked at regular intervals by means of individual measurements.
You must have the measurements carried out by a notified body (measuring centre) in accordance with § 29b of the Federal Immission Control Act (BImSchG). You must draw up a measurement report on the results and submit it to the immission control authority responsible for you.
In most cases, the competent authority for installations that fall under the 13th BImSchV is Department 5, Environment, of the locally responsible regional council. In individual cases, a different responsibility may exist.
According to the Immission Control Competence Ordinance (ImSchZuVo) of the state of Baden-Württemberg, the following applies:
Departments 5, Environment of the respective locally responsible regional councils are the responsible immission control authorities for company premises on which
exists or is to be constructed.
Department 9, State Office for Geology, Raw Materials and Mining of the Freiburg Regional Council is also the state-wide competent immission control authority for
The locally competent lower immission control authority (district or city administration) is the competent authority for all other industrial sites that do not fall under the regulations described above.
If you have newly commissioned or significantly modified your system, you must have the measurements carried out for the first time after 3 months at the earliest and after 6 months at the latest. Subsequently, the measurements must be carried out at least every 3 years after the last measurement.
The measurement report must be submitted to the responsible immission control authority within 12 weeks of the measurement together with all documents.
Complete measurement report in accordance with Annex A of Guideline VDI 4220 Sheet 2 (November 2018 edition) with information on, among other things
None
There is no statutory processing time.
Please ensure that you submit the measurement report to the immission control authority responsible for your plant.
Gesetz zum Schutz vor schädlichen Umwelteinwirkungen durch Luftverunreinigungen, Geräusche, Erschütterungen und ähnliche Vorgänge (Bundes-Immissionsschutzgesetz -BImSchG):
Dreizehnte Verordnung zur Durchführung des Bundes-Immissionsschutzgesetzes (Verordnung über Großfeuerungs-, Gasturbinen- und Verbrennungsmotoranlagen - 13. BImSchV):
Machine generated, based on the German release by: Umweltministerium Baden-Württemberg, 16.01.2026
Stadt Kuppenheim
Friedensplatz
76456 Kuppenheim
Telefon: 07222/9462-0
Telefax: 07222/9462-150
stadt@kuppenheim.de